Eglinton Crosstown: How Not to Build a Railway in Toronto
The B1MOctober 1, 202514 min1,679,836 views
30 connectionsΒ·40 entities in this videoβThe Eglinton Crosstown Project
- π‘ The Eglinton Crosstown line, a 19 km light rail transit (LRT) project in Toronto, was intended to alleviate severe city congestion and provide a much-needed transit option.
- π Originally slated to open in 2020, the project has faced numerous delays, with no confirmed opening date, leading to significant public frustration.
Reasons for Delays and Issues
- π Tunneling work, completed by 2016, was followed by a four-year delay in removing the Tunnel Boring Machines (TBMs) due to their size and the need for disassembly underground.
- β οΈ Over 260 quality control and technical issues have plagued the project, including a section of track laid millimeters off-spec, which could have led to derailments and took two months to fix.
- ποΈ Unanticipated work was required to fix defects with 1950s-era station caissons and reroute embedded water pipes, causing further setbacks and pushing opening dates back.
- π» Software issues with the train control system (nerve sensor) have been persistent, requiring multiple versions by June 2024.
Toronto's Growing Pains and Infrastructure Challenges
- π Toronto is one of North America's fastest-growing cities, experiencing a population boom that strains existing infrastructure and housing.
- π Congestion is a major problem, with residents facing some of the worst travel experiences due to limited transit capacity and urban sprawl.
- π° Municipalities like Toronto own significant infrastructure but receive a small portion of tax dollars, contributing to a substantial funding gap for essential projects.
Project History and Cost Overruns
- π The Eglinton Crosstown project has a long and convoluted history, with previous subway and light rail plans being scrapped or altered over decades.
- πΈ The initial cost estimate of $9 billion has ballooned to a projected $13 billion, with the pandemic being a mitigating factor but not the sole cause of the overruns.
What Happens Next?
- π The Toronto Transit Commission (TTC) has taken control of the line, and extensive stress testing is underway.
- π§ While tunneling for the western extension is complete, the opening date for Phase 1 remains uncertain, and public trust in target dates has eroded.
- β Despite the nightmarish journey, the Eglinton Crosstown, once operational, has the potential to significantly transform travel in Toronto.
Knowledge graph40 entities Β· 30 connections
How they connect
An interactive map of every person, idea, and reference from this conversation. Hover to trace connections, click to explore.
Hover Β· drag to explore
40 entities
Chapters7 moments
Key Moments
Transcript54 segments
Full Transcript
Topics14 themes
Whatβs Discussed
Eglinton CrosstownToronto TransitLight Rail Transit (LRT)Infrastructure ProjectsConstruction DelaysProject ManagementUrban CongestionPublic TransportationTunnel Boring Machines (TBMs)Quality ControlCost OverrunsUrban SprawlMunicipal FinanceTransit Planning
Smart Objects40 Β· 30 links
LocationsΒ· 5
MediaΒ· 1
ProductsΒ· 9
ConceptsΒ· 22
PersonΒ· 1
CompanyΒ· 1
EventΒ· 1